Do-It-Yourself Repairs & Basic Wiring Projects:
How to Install a Subpanel
By Terry Peterman, the Internet Electrician
| Summary: In this article, we guide you
through the installation of a subpanel (or pony panel as it is sometimes referred to) in a house.
|
In this situation, the original panel was full to
the point of some circuits that were added since construction having
to be ‘double-lugged’ under existing breakers.

Figure 1 -
Original Panel
My customer had just
purchased the house, and he needed to renovate his basement in order
to accommodate his collection of reptiles, spiders, amphibians and
other creatures. It made for one of the most interesting conditions
I've ever had to work under!

Figure 2 - Cuddly Snake!

Figure 3 -
Original Panel Cover Removed
Planning
The first step
should always be planning, as a project such as this is
fairly complex. Take the time to think through the necessary steps
to complete the job, ensure that you have the appropriate tools and
materials, and that all appropriate safety requirements are being
followed.
Remember -
Safety First! If you are at all unsure about tackling a
project like this, leave it to a reputable electrical contractor.
Good lighting is
critical when working on this type of project, so I would recommend
that you arrange for an external light source, such as a good
battery operated light, or a portable generator outside.
Run in an
extension cord to a portable work light, or a trouble light. This
will allow you to work in the original panel to make the required
changes with the main breaker off, which will de-energize the
bus bars in the panel.
Look at the area
you have to work with and decide where you are going to mount the
subpanel. Keep in mind that you don’t have to install it right
beside the original panel if space is an issue.
If the
planned renovations are in the opposite end of the house from the
original panel, you may want the subpanel closer to that area. This
would result in using a longer length of the heavier, more expensive
wire to feed the sub, but you would use less wire in all the branch
circuits added in the renovation.
In this case,
the service board has plenty of room to the left of the original
panel, and the room that the panel is in doesn’t have a finished
ceiling, so running new wires to the sub will be easy to do from
anywhere in the basement that the renovation will take place.
Now prepare
the panel for mounting by removing all covers.

Figure 4 - Remove the Subpanel Cover
Preparing the Subpanel
Mount the panel at a comfortable height for working on, and for
re-setting breakers etc. A good rule of thumb is about 5 feet from
the floor to the center of the panel.

Figure 5 - Mounting the Subpanel
Use the top key-hole screw
slot in the back of the panel to hang it, and using a level, hold
the panel in place, and use the remaining mounting holes to secure
the panel to the mounting board. (At least 4-#10 wood screws for a
panel this size).
Removing
Circuits
I’ve chosen to remove a 3-wire (two 15A breakers) that feed some
kitchen counter split receptacles, and two 2-wire branch circuits
(as these were double-lugged already) to make room for the 2 pole
40A breaker to feed the new subpanel.

Figure 6 & 7 - Removing Circuits

Cutting in the
Cables
Next, cut in the
cables that were removed from the existing panel into the new tub,
and the new subfeed cable interconnect between the two panels.
I am using #8AWG
3-conductor NMD-90 wire for the interconnect (Range cable). Make
sure you use approved cable connectors where you bring cables in
through the knock-outs in the panels.
Notice that I
installed the subpanel with the main breaker compartment at the
bottom. This was to accommodate the existing and the future branch
circuits that will enter the subpanel in the top and the sides of
the panel.

Figure 8 - Branch Circuits
into New Subpanel

Figure 9 - Installing Subfeed
into New Subpanel
I chose these
circuits, as the wires were long enough to cut into the new subpanel
without spicing.
This particular
panel is a Westinghouse ‘Nova-Line’ panel, and Westinghouse has
since been bought out by Cutler-Hammer.
The breakers
used in this panel are called ‘quads’, and ‘tandems’ or DNPL style.
They are a ‘push-in’ breaker, as opposed to a ‘bolt-in’ style.
These panels
will also accommodate a ‘BR’ style breaker, but they take up one
whole breaker space alone, as they are twice as wide.
One thing to
check is that some of the older Westinghouse breakers will not fit
in the new Cutler-Hammer panels, as the mounting tabs are slightly
different.
A new
Cutler-Hammer breaker will fit in the Westinghouse panel, but in the
case here, the breakers I removed from the original will not fit in
the new tub.
I will use a
15-40-40-15 DNPL breaker to feed the subpanel. The two 40A breakers
in the middle (split across both hot busses of the panel) will feed
the new sub, and the two 15A circuits on the outside will be used to
feed the existing circuits that will now have their own breakers,
instead of being double-lugged (which is against any and all rules
that I’m aware of!).
The Subpanel

Figure 10 - Subfeed Connected to Subpanel

Figure 11 - Making Room for Subpanel Breakers
The panel I
chose to use here is a Cutler-Hammer model # CPM-120. This is a
panel with a main breaker, and space for 20 BR style breakers, or 40
circuits in the DNPL style. This will give us more than enough
breaker space for the planned renovation, as this subpanel is bigger
than the original.
We also would
not require a main breaker in this subpanel because a disconnect
exists right beside it in the original panel. I used this panel
with a main breaker because it is more inexpensive (about 30% less)
than one with main lugs. (They tell me that because they manufacture
more panels with a main breaker, the cost goes down, due to
volume). That aside, it makes no difference whether you feed the
buss bars in the subpanel via main lugs, or through a main breaker;
the results are the same.
The 100Amps main
is providing over-current protection for the buss bars, and not any
of the branch circuits, and the subpanel current is limited to
40Amps by the subpanel feed breaker in the main panel.
Making Your Connections
At this
point, you could make your connections to the subfeed breaker in the
main panel, and re-install the panel cover.
Leave the
subfeed breaker off, but now you could turn the main breaker in the
original panel back on, and restore power to the house and get the
lights, heat, etc. back working again.

Figure 12 - Installing Subfeed into Subpanel
When installing
cables into a panel, connect the bare ground wires first, then the
neutral (white) wires to the neutral buss, and finally, install the
breakers and connect the hot wires (red or black) to the breaker
lugs.
Always take the
time to make the wires look neat and orderly, as it not only looks
good, but saves time tracing wires, if necessary, in the future.
The same goes
for the connections to the main lugs (or in this case the main
breaker) in the subpanel. Make sure that you bring the subfeed
cable into the main breaker compartment of the subpanel.

Figure 13 - Subfeed Connected to Breaker
Neutral
Bonding Jumper
This would be a
good time to talk about the neutral bonding jumper.
In most panels
you will find that the neutral buss bar (the common bar that is
mostly isolated from the panel case), has either a long brass
machine screw, or a metal strap of some kind that connects the
neutral bar to the panel case, or ground.
In a subpanel,
the neutral must be totally isolated from ground, so you must remove
this screw or strap. The neutral and the ground can only be bonded
in one location in a residential service, and that is in the main
panel.

Figure 14 - Bonding Jumper Removed

Figure 15 - Bonding Jumper
The sub-feed
cable then connects like this:
-
bare ground
wire to a case ground lug, the white neutral wire to an
appropriately sized lug on the now isolated neutral bar, and the
red and black hot wires to the lugs of the main breaker in the
subpanel.
As is the case
in the main panel, you are reverse feeding the main breaker, which
then feeds power through to the panel’s hot buss bars that the
branch circuit breakers connect to. (Clear as mud, or did I lose you
now?)
Final
Connections
Now connect the
branch circuit wires in the same order:
Once all the
connections are made, you can install the main compartment barrier,
and then remove the appropriate knockouts in the panel cover, and
install it.
Turn on the
sub-feed breaker in the main panel, followed by the subpanel main,
and then the branch circuit breakers.
If no sparks
fly, and the circuits that you moved to the subpanel now work,
you’ve done a great job, and you now have the room you need to
accommodate the additional circuits that will be added during the
upcoming renovation project.

Figure 16 - The Final Product
Labeling the
Panel
The final step
is to label the panel in order to identify which breaker feeds what;
a step that is all too often over-looked, but any good inspector
will catch you on this one, and make you label the circuits before
giving his/her final acceptance.

Figure 17 - Labeling the Panel
Now my job
here is done, and I can get out of here before my customer's Burmese
Python starts “Wrappin’ himself around me!

Figure 18 - Customer Dean Harper, Owner of "Wrappin'
About Reptiles" and His Python Friend
Do you need additional help or clarification on
this or other home wiring topics? Click here ...
Back to Do-it-Yourself Repairs & Basic Wiring Projects
Articles Page -
Click Here ...
Back to Articles Main Page - Click Here
....
|